Job No. |
Client/Main Contractor |
Project |
Description of Work |
2019-124 |
Alchmex – Paul Y Joint Venture |
HY/2018/02 Central Kowloon Route – Kai Tak East |
CCTV Inspection of Nullah
Removal of silt at Kai Tak River
Condition survey to Kai Tak River box culvert
|
2019-116 |
CLP Power Hong Kong Ltd., |
Castle Peak Power Station |
Inspection and desilting |
2019-114 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
Annual maintenance work to intake heads, dosing pipe and forebay |
2019-107 |
Kum Shing Electrical & Mechanical |
Black Point Power Station A Cooling Water Pumphouse |
Plug and unplug the seawater manifold |
2019-103 |
Architectural Services Department |
Kwun Tong Swimming Pool |
Repair the loosen pool tiles and defective hollow render |
2019-093 |
PMPS Liner Technology (Hong Kong) Ltd., |
Contract No. DC/2015/02 Drainage Maintenance and Construction |
Inspection to outfall pipe |
2019-068 |
Chu Kong Group Shipyard Co., Limited |
Skypier Pontoons’ Mooring System |
Replacement of hawsers and superflexes for Hoi Tin I and II |
2019-067
|
CLP Power Hong Kong Ltd.,
|
Castle Peak Power Station
|
Condition survey and pile thickness measurement |
2019-065
|
Paul Y Construction Co. Ltd., |
Contract No. 19-83003 South Horizons (West) and Luk Chau Wan (Sea Portions) |
Remedial works for 275-kV Cable Landing Points |
2019-054 |
The Hongkong Electric Co. Ltd. |
Contract no. 19-81003 Refurbishment of East Wharf at Lamma Power Station |
Replacing Existing Turnbuckle of Frontal Frame No.3 |
2019-042 |
The Jardine Engineering Corporation Ltd., |
Lamma Power Station |
Upgrading of Marine Fenders at West Heavy Unloading Area |
2019-035 |
Prominent Environmental Ltd., |
Hong Kong International School |
Inspection and assist to adjust the cable tension of the swimming pool |
2019-033 |
Welcome Const. Co. Ltd. – Riseway Const. Eng. Ltd. JV |
Contract No. DC/2015/02 Drainage Maintenance and Construction in Mainland South Districts Po Kong Village Road and Fung Tak Road |
Condition survey to box culvert |
2019-024 |
Chu Kong Group Shipyard Co., Limited |
Skypier Pontoons’ at Hong Kong International Airport |
CCTV inspection to the condition of Pontoon |
2019-009 |
ATAL Engineering Ltd., |
Existing Government Pumphouses at West Kowloon Cultural District |
Installation and removal |
2019-006 |
Alliance Professional Surveyors Co. Ltd. |
Kai Tak Temporary barging point |
Diving inspection to seawall and seabed |
2019-005 |
Victory Engineering Service Co. Ltd. |
Tender 1256EM18W Hong Kong Coliseum Seawater Pumphouse |
Plug and unplug off the water inlet |
2019-004 |
Fugro (Hong Kong) Ltd., |
Aviation Fuel Receipt Facility (AFRF) at Sha Chau |
Condition survey to all marine piles of MD1 |
2019-002 |
ERM-Hong Kong Ltd., |
Hong Kong Offshore LNG Terminal |
Supply, installation, removal and monitoring of C-Pod |
|
|
|
|
2018-127 |
Ciel & Terre China, |
Shek Pik Reservoir |
Replacement of mooring system |
2018-120 |
Chu Kong Group Shipyard Co. Ltd. |
Sky Pier: Hong Kong International Airport |
Seabed Detection at Jetty Pier |
2018-102 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
Annual maintenance work to intake heads, dosing pipe and forebay |
2018-098 |
Kum Shing Group, |
Castle Peak Power Station A Cooling Water Pumphouse |
Dimensional survey to seawater manifold |
2018-094 |
Fyfe (Hong Kong) Ltd., |
Eastern Harbour Crossing Tunnel |
Inspection of seaside anode and reference electrodes |
2018-093 |
TIML MOM Ltd., |
Marine Works within the TMCA |
Marine Diving Inspection for features and facilities |
2018-075 |
The Hong Kong Shipyard Ltd., |
The Hong Kong Shipyard Jetty Pier |
Supply and installation of silt curtain on the west side of jetty pier |
2018-068 |
Sun Fook Kong(Civil)Ltd., |
Contract No. DC/2009/10 harbour Area Treatment Schage 2A Upgrading Work |
Installation and Remover of Bulkheads |
2018-065 |
REC Engineering Co. Ltd., |
Cheung Sha Wan Wholesale Food Market |
Fabrication, installation and removal of temporary bulkhead |
2018-060 |
Welcome Const. Co. Ltd. – Riseway Const. Eng. Ltd. JV |
Contract No. DC/2013/07 Drainage Maintenance & Construction in Mainland North District (2015-2019) |
CCTV inspection to box culvert at Lung Sum Avenue |
2018-059 |
Drainage Services Department, |
Contract No. DC/2016/02 Building & Civil Maintenance & Minor Worksto DSD Plants and Facilities (2016-2020) |
Penstocks Leakage Mitigation Measures at Tsing Yi PTW, To Kwa Wan PTW, Kwun Tong PTW and Kwai Chung PTW |
2018-057 |
New World Construction Co. Ltd., |
14104 Avenue of Stars |
Condtion survey works to existing seawall |
2018-049 |
Lucky Engineering Co. Ltd. |
Stonecutters Island Naval Base Seawater Pumphouse |
Assist to lift up the barscreen |
2018-048 |
Prominent Environmental Ltd., |
Hong Kong International School |
Annual inspection to swimming pool movable floor |
2018-046 |
Modern Terminals Ltd., |
Kwai Chung Container Terminal No. 2 |
Check the sheetpiles condition |
2018-038 |
Welcome Const. Co. Ltd. – Riseway Const. Eng. Ltd. JV |
Contract No. DC/2015/02 Drainage Mainteance and Construction in Mainland South Districts (2015-2019) |
CCTV inspection to decked nullah |
2018-031 |
TJ Engineering Services Ltd., |
World Wide House, 19, Des Voeux Road Central |
Supply and Replacement of the Penstocks at Sea Water Pump Room |
2018-028 |
CLPe Solutions Ltd. |
Contract T17M202 – Underwater Facilities Hongkong International Airport |
Supply and reinstate the Fiberglass staircase at SWPH1 |
2018-027 |
P & A Engineering Ltd., |
Kowloon Park Swimming Pool |
Installation and Removal of Support Stands |
2018-020
|
Drainage Services Department, |
Contract No. DC/2016/02 Building & Civil Maintenance & Minor Works to DSD Plants and Facilities (2016-2020) |
Robotic CCTV Inspection and Leakage Mitigation Works of the Submarine Outfalls of Chai Wan Preliminary Treatment Works (PTW) |
2018-017 |
Wise Engineering & Surveying Co. Ltd., |
DSD Contract No. DC/2009/24 HATS Stage 2A – Upgrading of Preliminary Treatment Works at Sandy Bay, Cyberport, Wah Fu, Aberdeen and Ap Lei Chau
|
Diver Survey for Existing Seawall at Ap Lei Chau |
2018-009
|
TJ Engineering Services Ltd.,
|
World Wide House, 19, Des Voeux Road Central
|
Cleaning the guide rail and mesh screen |
2018-008 |
CRBC-Build King Joint Venture, |
Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel – Road P2 and Associated Works |
CCTV and silt thickness measurement to 1350mm Ø drainage pipe |
|
|
|
|
2017-136 |
Hsin Chong Construction Co. Ltd., |
Main Works for M+ Museum Project at West Kowloon Cultural District |
Dismantling the existing intake screen in seawater pump cell No. 13 at Seawater Side |
2017-135 |
Shiu Wing Steel Ltd., |
Shiu Wing Steel Mill, Area 38 |
Removal of silt inside the intake chamber |
2017-124 |
Sun Fook Kong – Biwater Joint Venture, |
Contract No. DC/2009/10 Harbour Area Treatment Scheme Stage 2A Upgrading Works at Stonecutters Island Sewage Treatment Works – Main Pumping Station, Sedimentation Tanks and Ancillary Facilities |
Dimension survey for existing connecting audit |
2017-121 |
Paul Y Builders Ltd., |
Residential Development at 9, Muk Ning Street, NKIL 6527 |
Plug and unplug off the 600mm Ø stormwater pipe |
2017-117 |
MCW Marine Services Ltd |
kypier Pontoons’ at Hong Kong International Airport |
CCTV inspection to the condition of Pontoon |
2017-116 |
MCW Marine Services Ltd |
Contract No. DC/2015/02 Drainage Mainteance and Construction in Mainland South Districts (2015-2019) Waterloo Road Box culvert
|
CCTV to investigate the box culvert condition |
2017-110 |
Drillcut Ltd., |
Contract No. DC/2009/10 Harbour Area Treatment Scheme – Stage 2A Upgrading works at Stonecutters Island Sewage Treatment Works |
Provision of diving team to assist underwater cutting works |
2017-109 |
Biwater Man Lee Ltd., |
West Kowloon Seawater Pumphouse |
Installation and Removal of Plug |
2017-107 |
CRBC-Build King Joint Venture, |
Contract No. NE/2015/02 Tseung Kwan O – Lam Tin Tunnel – Road P2 & Associated Work |
Installation and welding of steel plate to cover temporary cofferdam type 2 gap by Diving Method |
2017-106 |
Paul Y. Construction Co. Ltd., |
Contract No. DC/2016/02 Building & Civil Maintenance & Minor Works to DSD Plants and Facilities (2016-2020) Submarine Outfalls of Shau Kei Wan Preliminary Treatment Works |
Robotic CCTV Inspection and Leakage Mitigation Works of the |
2017-103 |
Chu Kong Group Shipyard Co., Limited |
Skypier Pontoons’ at Hong Kong International Airport |
CCTV inspection to the condition of Pontoon |
2017-096 |
Fyfe (Hong Kong) Ltd., |
Eastern Harbour Crossing Tunnel Cathodic Protection Design |
CCTV inspection to anodes and reference electrodes |
2017-095 |
Chu Kong Group Shipyard Co., Limited |
Skypier Pontoons’ Mooring System Hong Kong International Air |
Provision of Protection & Indemnity to Working Boat |
2017-092 |
Welcome Construction Co. Ltd. |
Northern Area Phase II, West Kowloon Reclamation |
Dimensional survey to box culvert and equalizing hole |
2017-085 |
Dongah Geologicial Engineering Co. Ltd., |
Vessel: Dong J-1 No. 5 |
Cutting of Rig |
2017-078 |
Kiu Lok Service Management Co. Ltd., |
Seawater Intake of the New Seawater Supply System at New World Centre 18-24, Salisbury Road, Tsim Sha Tsui, Kowloon (2017-2018) |
Cleaning and Inspection |
2017-074 |
M.Y. Cheng & Co. Eng. Ltd., |
Castle Peak Power Station |
Plug and unplug off the B1 and B2 intake pipe |
2017-070 |
Leighton-China State Joint Venture |
SCL1123 – Exhibition Station and Western Approach Tunnel T0255 |
Area E – Fabrication, Installation and Dismantling of Temporary Steel Bulkheads in Box Culvert |
2017-059 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
CCTV inspection and Dimensional survey to SCWP intake culvert |
2017-045 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
Inspection, cleaning and desilting work |
2017-041 |
Hsin Chong Construction Co. Ltd., |
Main Works for M+ Museum Project at West Kowloon Cultural District |
Underwater Inspection and Capping off/ Uncapping of Existing Water Pipe |
2017-036 |
Prominent Environmental Ltd., |
Hong Kong International School Lower Primary School Redevelopment Repulse Bay Campus, Hong Kong.
|
Connection of wire to the pulley system of swimming pool |
2017-026 |
TJ Engineering Services Ltd., |
World Wide House, 19, Des Voeux Road Central |
Cleaning the guide rail and mesh screen |
2017-025 |
Yee Hop Construction Co. Ltd., |
Castle Peak Power Station |
CPPS Jetty – Pile Thickness Measurement & Pile Wrapping System |
2017-016 |
CLP Engineering Ltd., |
Tender Ref. WSD/ST454/16 Supply and Installation of a Floating Solar Power System at Plover Cove Reservoir |
Installation of Anchoring system |
2017-003
|
Wise Engineering & Surveying Co. Ltd.,
|
XRL 811B – WKT Approach Tunnel (South) Nam Cheong Barging Point Reinstatement
|
Condition survey to seawall |
2017-002 |
REC Engineering Co Ltd., |
Shek Pik Reservoir |
Underwater Anchoring Installation Underwater diving services |
2016-148 |
Tong Kee Engineering Ltd., |
Castle Peak Power Station Jetty Refurbishment Works |
Provision of diving team to assist underwater works |
2016-138 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
Inspection, cleaning and desilting work |
2016-132
|
Ciel & Terre China,
|
Shek Pik Reservoir Underwater Anchoring Installation
|
Underwater diving services |
2016-128 |
Top Exxpress Construction Engineering Ltd., |
Contract No. DC/2013/01 Tolo Harbour Sewerage of Unsewered Areas, Stage 2 Phase 1 |
CCTV inspection to condition of box culvert |
2016-123 |
Samsung – Build King JV, |
Three Runway System Project Contract 3202, Deep Cement Mixing Works (Package 2) |
Underwater Diving Inspection |
2016-120 |
CLP Power Hong Kong Ltd., |
Castle Peak Power Station |
Removal of marine debris at B4 Drum Screen Pit |
2016-119 |
Castle Peak Power Station |
Castle Peak Power Station |
Demolish the B4 No. 11 Coarse Screen |
2016-112 |
Dragages-Bouygues Joint Venture, |
MTR SCL Contract 1128 Shatin to Central Link (Hong Kong Section) |
Removal of blockage inside 1200mm Ø storm water pipe |
2016-109 |
BMT Asia Pacific Ltd., |
Skypier Pontoons’ at Hong Kong International Airport |
CCTV inspection to the condition of Pontoon |
2016-105 |
CLP Power Hong Kong Ltd., |
Castle Peak Power Station |
Inspection and Desilting to CW forebay, CPB Station |
2016-100 |
Welcome Construction Co. Ltd. |
The Public Housing Department at Cheung Sha Wan Wholesale Food Market Site 3 and Site 5 |
Design, Fabricate and Installation of Temporary Bulkhead for Fat Tseung Street Culvert |
2016-082 |
China Harbour Construction Co. Ltd. |
MTR SCL Contract 1128 Shatin to Central Link (Hong Kong Section) |
Strengthening the column with Quad Shore |
2016-081 |
Jacobs China Ltd., |
Permanent Aviation Fuel Facility |
Services for PAFF Jetty Structural Inspection |
2016-073 |
Tai Ah Engineering Co. Ltd., |
Kwun Tong SPS |
Plug and unplug the sump inlet penstocks |
2016-070 |
CLP Power Hong Kong Ltd., |
Castle Peak Power Station |
Inspection to North and South Lagoon |
2016-069 |
Winning Engineering & Consultants Co., |
Stonecutters Island Naval Base Seawater Pumphouse |
Plug and unplug the seawater intake pipe |
2016-068 |
Unison Construction Engineering Ltd., |
Shatin Sewage Treatment Works |
Assist the lifting of pump inside the aeration tank |
2016-067 |
WCCL-RCEL JV |
Contract No. DC/2015/02 Mainland South Division Drainage maintenance & Construction in Mainland South Districts (2015-2019) |
Installation and removal of contaminated boom |
2016-066 |
Wenden Engineering Service Co. Ltd. |
Government Office at Yaumatei Seawater Pumphouse |
Plug off the seawater intake |
2016-056
|
Chu Kong Group Shipyard Co., Limited
|
Skypier Pontoons’ Mooring System Hong Kong International Airport
|
Provision of Protection & Indemnity to Working Boat |
2016-037 |
Modern Terminals Ltd., |
Ref. No.: 331-Q20013-JL Terminal 5 Quay Piles Condition Survey (Phase 2) |
Variation work – Condition survey for additional piles |
2016-029 |
ERM-Hong Kong Ltd., |
South of Lantau Island between Shek Kau Chau and Soko Islands |
Placing of monitoring C-Pod device and holder |
2016-028 |
TJ Engineering Services Ltd., |
World Wide House, 19, Des Voeux Road Central |
Cleaning the guide rail and mesh screen |
2016-025 |
Sun Fook Kong – Biwater Joint Venture, |
Contract No. DC/2009/10 Harbour Area Treatment Scheme Stage 2A – Upgrading Works at Stonecutters Island Sewage Treatment Works – Main Pumping Station, Sedmentation Tanks and Ancillary Facilities |
Underwater works of Riser Shaft |
2016-003 |
Far East Engineering Services Ltd |
Shun Tak Centre Seawater Intake |
Repairing the existing travelling band screen |
|
|
|
|
2015-141 |
Fu Lam Construction Engineering Co. Ltd., |
Shun Tak Centre Seawater Intake |
Supply Ham Baker Adams Penstocks & Travelling band Screens |
2015-132 |
CLP Power Hong Kong Ltd., |
Black Point Power Station |
Diving works at BPPS and CPPS |
2015-124 |
Welcome Construction Co. Ltd., |
DSD Contract No. 2012/11 Drainage Maintenance & Construction in Hong Kong Island and Islands District (2013-2017) |
Condition survey to the 4th box culvert off the seawall beyond Golden Bauhinia Square |
2015-121 |
Chun Wo-CEC Joint Venture, |
Strategic Sewage Disposal Scheme Stage I – Principal Collection & Treatment System |
Inspection to existing box culvert for Effluent Water Discharge at Stonecutters Island |
2015-104 |
Arup, |
Sham Tseng Submarine Outfall |
Condition survey with Remote Operated Vehicle |
2015-075 |
Shun Yuen Construction Co. Ltd., |
Contract No. DC/2012/01 Building & Civil Maintenance & Minor Works to DSD Plants and facilities (2012-2016) |
Inspection to Shatin twin submarine outfall with Remote Operated Vehicle |
2015-062 |
Paul Y Construction Co. Ltd., |
Project 15/8016 Refurbishment of North Jetty Approach |
Strengthening of Pile & Bracing for Pile No. P207-P209 |